RenoNext
Price CheckStart Project
verifiedRenoNext Verified Service

Home Additions

An addition is a new building attached to an old one — and the junction where they meet is where everything goes wrong. Differential settlement, thermal bridging, and roof valleys that leak.

Project Overview

schedule
Timeline
4-8 months from design to occupancy (2-4 weeks design, 6-12 weeks permit approval, 12-20 weeks construction, 1-2 weeks inspections)
speed
Difficulty
High — requires coordination of structural engineer, architect/designer, multiple trades, and municipal approvals. Foundation work, structural integration, and weatherproofing are critical phases.
payments
Starting at
$60,000-$120,000
thermostat
Best Season
Foundation and framing best done in dry, warm weather (May-October). Winter construction possible but slower and costlier due to frost protection, heating, and material handling.
shield_with_heart

Escrow Protected

Funds held until milestones verified

infoOverview

What is home additions?

A home addition is new floor area built onto an existing house — rear extensions, side additions, second-storey builds, or bump-outs. Unlike renovations (which work within existing footprint), additions create new enclosed space and require full compliance with current building codes, zoning bylaws, and setback rules.

The defining challenge is **structural integration**: the addition must attach to the existing house without causing differential settlement (new foundation settles differently from old), thermal envelope failure (air leakage and thermal bridging at the junction), or roof leakage (valley flashing, step flashing, and tie-ins are the weak points). Most additions fail at the interface, not within the new construction itself.

**Foundation options:** If building a ground-floor addition, you need a foundation. Two approaches: (1) **Independent foundation** — pour new footings and walls alongside the existing foundation but not structurally connected. This allows independent settlement (old house won't crack if new addition settles), but you need an expansion joint at the interface and careful detailing to prevent water infiltration. (2) **Tied foundation** — dig down to expose existing footings, drill rebar into old concrete, pour new footings and walls tied to existing. This creates a monolithic structure but risks cracking if soils differ or if the existing foundation is weak. Most engineers prefer independent foundations with proper flashing and sealant at the joint.

**Structural load paths:** The new addition's loads (roof, floor, walls) must transfer to the new foundation — not dump onto the existing house. If adding a second storey, the existing foundation and framing must carry the added load. This often requires upgrading: new footings under existing walls (underpinning), sistering floor joists, adding steel beams, or reinforcing existing foundations. A structural engineer calculates existing capacity and designs upgrades.

**Roof tie-ins:** Connecting a new roof to an existing roof creates valleys (where two roof planes meet at an angle). Valley flashing must handle high water flow — water from both planes converges and runs down the valley. Use ice/water shield underlayment, metal valley flashing (24-gauge galvanized or aluminum), and ensure shingles overlap correctly (woven valley or cut valley, never closed valley). **Crickets (saddles)** are required behind chimneys or other roof penetrations wider than 30" — a small peaked structure that diverts water around the penetration, preventing ice dams and pooling.

**Thermal envelope and air sealing:** The junction between old and new is the weakest point for air leakage and heat loss. Spray foam at the seam (closed-cell, 2" minimum for R-12 and air barrier) is the most reliable solution. Batt insulation alone fails because it doesn't seal air gaps. Pay attention to the transition from old wall sheathing to new — tape joints with Tyvek or Blueskin to maintain continuity of the air and water barrier.

**Zoning and setbacks:** Every municipality has zoning bylaws that limit how close you can build to property lines (setbacks), how much of your lot you can cover with structures (lot coverage, typically 30-35%), and maximum height. Toronto example: front yard setback 25 feet (7.5m), rear yard setback 7.5m, side yard setback 0.45m per metre of building height. Most additions exceed one of these limits and require a **Committee of Adjustment minor variance** — a public hearing where neighbours can object. Process takes 6-12 weeks and costs $1,000-$3,000 in application fees plus potential consultant fees (planner, lawyer). Approval is not guaranteed — neighbour objections can sink a project.

When you need home additions

  • check_circle
    You need more living space but moving is too expensive or disruptive
  • check_circle
    Your lot is large enough to accommodate setbacks and lot coverage rules
  • check_circle
    You want to add a primary bedroom suite, home office, or family room
  • check_circle
    Adding a second storey to increase floor area without expanding footprint
  • check_circle
    Bumping out a kitchen or bathroom by 4-8 feet to improve layout
  • check_circle
    Your existing foundation can support added load (or you're willing to upgrade it)
  • check_circle
    You're prepared for a 4-8 month project with 6-12 weeks of permit delays
  • check_circle
    You can afford $200-$400 per square foot for quality construction
timelineStep by Step

The Process

What happens from start to finish

1

1. Feasibility and Zoning Review

1-2 weeks

Measure your lot and existing house. Check zoning bylaws for setbacks, lot coverage, and height limits. Most municipalities publish zoning maps and bylaws online. Calculate whether your proposed addition fits within zoning rules — if not, you'll need a Committee of Adjustment variance (adds 6-12 weeks and $1,000-$3,000). Verify services capacity: does your electrical panel have room for new circuits, or do you need a service upgrade? Is your HVAC system sized for the added square footage, or do you need a second system? Check for easements, rights-of-way, or building restrictions on your property (title search, $75-$150).

2

2. Design and Structural Engineering

3-6 weeks

Hire an architect or designer to create floor plans, elevations, and sections showing the addition. The designer coordinates with a structural engineer who assesses existing foundation and framing capacity, designs new foundations and beams, and specifies tie-in details. Expect drawings showing: foundation plan (footings, walls, bearing points), framing plan (joists, beams, rafters), roof plan (tie-ins, valleys, flashing), wall sections (insulation, air barrier, cladding), electrical and plumbing rough-ins. Cost: $3,000-$8,000 for design, $1,500-$4,000 for structural engineering.

3

3. Committee of Adjustment Variance (if needed)

6-12 weeks

If your addition violates setbacks, lot coverage, or height limits, apply for a minor variance. Submit application with drawings, site plan, and fee ($1,000-$2,000). The Committee schedules a public hearing (6-10 weeks out). Neighbours within 60 meters are notified and can attend to support or object. The Committee grants or denies the variance based on four tests: Does the variance maintain the general intent of the zoning bylaw? Is it desirable for the development of the land? Is it minor in nature? Does it maintain the general intent of the official plan? Approval is common for reasonable requests, but neighbour opposition complicates things. Hire a land-use planner ($1,500-$3,000) if the request is contentious.

4

4. Building Permit Application

4-8 weeks

Submit drawings and structural letters to the municipal building department with permit application fee ($1,500-$4,000 depending on project value). Review takes 4-8 weeks. Common revision requests: structural detail clarifications, energy code compliance (R-values, window ratings), fire separation if the addition creates a second dwelling unit, egress window sizing. Some municipalities require HVAC drawings, plumbing isometric drawings, or energy models (EnerGuide). Once approved, you receive a building permit and can start construction.

5

5. Site Prep and Excavation

3-5 days

Stake out the addition footprint (string lines and batter boards). Call Ontario One Call (1-800-400-2255) for utility locates — gas, hydro, water, sewer, telecom must be marked before digging. Excavate for footings — dig below frost line (4 feet / 1.2m in Ontario) to prevent frost heave. If building alongside existing foundation, dig carefully to avoid undermining it (excavate in short sections, brace if needed). If soils are poor (clay, fill, high water table), engineer may specify deeper footings, wider footings, or engineered fill (clear stone, compacted granular).

6

6. Foundation Pour

1-2 weeks

Build footing forms, install rebar (typically #4 or #5 bars, 18" spacing), pour concrete (3000-4000 PSI). Footings must cure 3-7 days before loading. Build foundation wall forms (ICF blocks, wood forms, or aluminum panels), install vertical rebar tied to footing rebar, pour walls. If tying to existing foundation, drill and epoxy rebar into old concrete before pouring. Install weeping tile around perimeter (4" perforated pipe in clear stone jacket, sloped to sump or daylight drain). Damp-proof exterior of foundation walls (rubberized asphalt or spray-on membrane). Inspection: footing inspection (before pour), foundation wall inspection (before backfill).

7

7. Framing (Floors, Walls, Roof)

3-5 weeks

Install sill plates on foundation (pressure-treated 2x6, anchored with foundation bolts). Frame floor joists (typically 2x10 SPF at 16" O.C. — check engineer's span tables). Install subfloor (3/4" tongue-and-groove OSB or plywood, glued and screwed). Frame exterior walls (2x6 at 16" O.C. for R-20+ insulation) and interior partition walls (2x4 at 16" O.C.). Install headers over windows and doors (doubled 2x10 or LVL per engineer). Raise and brace walls. Frame roof — rafters or trusses per engineer's design. Tie into existing roof structure: sister new rafters to existing, install valley rafters, flash valleys with ice/water shield and metal flashing. Install roof sheathing (1/2" or 5/8" OSB). Inspection: framing inspection (critical — inspector checks structural connections, bearing points, beam sizes, roof tie-ins).

8

8. Exterior Envelope (Roofing, Windows, Siding)

2-4 weeks

Install roofing underlayment (synthetic or ice/water shield in valleys and eaves), shingles, flashings (step flashing, valley flashing, kick-out flashing, chimney crickets). Install windows and exterior doors (rough opening must match window size — shim and flash per manufacturer specs). Install house wrap (Tyvek or similar) over sheathing, tape seams. Install siding to match existing (brick, vinyl, fiber cement, stucco) — matching brick coursing and mortar color is tricky; vinyl is easier. Seal the junction between old and new with flashing and caulk (butyl or polyurethane, not acrylic).

9

9. Rough-Ins (Electrical, Plumbing, HVAC)

2-3 weeks

Run electrical: new circuits from main panel or sub-panel, outlets (12" above floor, 4' spacing on walls), switches, lights, smoke/CO alarms. Rough-in plumbing if adding bathroom or kitchen: drain lines (slope 1/4" per foot), vent stack (extends through roof or ties to existing vent), supply lines (PEX or copper, hot on left). Install HVAC: extend existing ductwork or add new system (furnace, AC, heat pump). Inspections: rough electrical (ESA), rough plumbing, rough HVAC/gas (TSSA if applicable).

10

10. Insulation and Vapour Barrier

1-2 weeks

Insulate exterior walls (R-20 minimum for 2x6 walls — batt or spray foam), ceiling/roof (R-50 minimum in Ontario — blown cellulose or spray foam). Spray foam at the junction between old and new structure (closed-cell, 2" minimum) to seal air leaks. Install vapour barrier (6-mil poly) on warm side of insulation in heated spaces, tape seams. Inspection: insulation inspection (before drywall).

11

11. Drywall, Finishes, Trim

4-6 weeks

Hang drywall (1/2" for walls, 5/8" for ceilings), tape and mud joints, sand smooth, prime and paint. Install flooring (hardwood, laminate, LVP, tile). Install interior doors, baseboards, casing, crown moulding. Connect electrical devices (outlets, switches, fixtures). Connect plumbing fixtures (sinks, toilets, showers). Install cabinets and countertops if adding kitchen or bathroom.

12

12. Final Inspections and Occupancy

1-2 weeks

Book final inspections: building final (structure, envelope, fire separation if applicable), ESA final (electrical), plumbing final, HVAC/gas final. Install smoke and CO alarms (interconnected per OBC 9.10.18). Inspector will verify all code requirements, check handrails on stairs (34"-38" height, graspable profile), test GFCI outlets in kitchens/bathrooms, verify egress windows in bedrooms. Once all inspections pass, receive occupancy permit and move in.

paymentsPricing Transparency

Investment Guide

Addition costs range from $200-$400 per square foot depending on complexity, finishes, and site conditions. A simple one-storey rear extension on a slab is cheaper than a second-storey addition requiring foundation upgrades and complex roof tie-ins. Budget 15-25% for design, permits, and contingencies.

diamond

One-Storey Rear Addition (200-400 sq ft, slab foundation)

$60,000-$120,000

Depends on: Simple rectangular footprint, slab-on-grade foundation, basic finishes, shed roof or gable roof. Includes foundation, framing, roofing, siding, windows, insulation, drywall, flooring, electrical, HVAC extension. Does not include kitchen or bathroom fixtures.

One-Storey Side Addition (300-500 sq ft, full foundation)

$90,000-$150,000

Depends on: Full foundation (footings and walls), integration with existing structure, more complex roof tie-in (valley), matching exterior finishes. Includes all trades, mid-grade finishes.

Second-Storey Addition (500-800 sq ft)

$150,000-$280,000

Depends on: Requires foundation assessment and potential upgrades (underpinning, sistering joists, adding beams). Roof removal and rebuild. Stairs from first to second floor. Staging and material hoisting. Includes new roof over entire house (tie-in complexity). High structural engineering costs.

Bump-Out Addition (50-100 sq ft, cantilevered or on posts)

$20,000-$40,000

Depends on: Small extension for kitchen, bathroom, or closet. Cantilevered floor (no foundation) or posts on concrete piers. Minimal foundation work, limited roof modification. Good for gaining functional space without major construction.

Design and Engineering Fees

$5,000-$12,000

Depends on: Architectural drawings ($3K-$8K), structural engineering ($1.5K-$4K), land surveyor if needed ($800-$1,500). Complex designs or second-storey additions cost more.

Permits and Approvals

$2,000-$6,000

Depends on: Building permit ($1.5K-$4K), Committee of Adjustment variance if needed ($1K-$3K), ESA/plumbing/HVAC permits ($400-$800 total).

descriptionPermits
warningPermit Required
Building Permit (Addition)$1,500-$4,000
Committee of Adjustment Minor Variance (if required)$1,000-$3,000
Electrical Safety Authority (ESA) Permit$150-$400

What Affects the Price

Foundation type: Slab-on-grade is cheapest ($8-$12 per sq ft), full foundation with basement is $25-$40 per sq ft. Foundation upgrades (underpinning, reinforcement) add $20K-$50K.Roof complexity: Shed roof or simple gable is straightforward. Complex roof tie-ins with valleys, crickets, and multiple planes add $5K-$15K in framing and roofing costs.Exterior finishes: Vinyl siding is $3-$6 per sq ft installed. Brick is $15-$25 per sq ft. Matching existing brick (coursing, color) is difficult and expensive — plan for higher costs.HVAC approach: Extending existing ductwork ($2K-$5K) is cheaper than adding a second system ($6K-$12K for furnace + AC). Mini-split heat pumps ($4K-$8K) are a middle option.Second-storey additions: Require structural upgrades to existing foundation and framing (often $30K-$60K), new roof over entire house ($15K-$30K), and staging/hoisting ($5K-$10K). Total cost: $200-$350 per sq ft.Finishes: Builder-grade (laminate, vinyl, basic fixtures) vs mid-range (hardwood, quartz, semi-custom cabinets) swings cost by $40-$80 per sq ft.Site access: Tight lots with no equipment access (must hand-dig, hand-carry materials) increase labour costs by 20-40%.Contingency: Budget 15-20% for unknowns — poor soils requiring deeper footings, hidden structural issues in existing house, permit delays, weather delays.

Get a detailed addition feasibility report and fixed-price quote — we'll assess your existing structure, confirm zoning compliance, and deliver a turnkey price with no surprises.

Get a ballpark estimate in under 2 minutes.

Try Price Checkarrow_forward
gavel

Permits & Building Code

Ontario Building Code requirements

Permit / ApprovalAuthorityTypical Cost
Building Permit (Addition)Municipal building department$1,500-$4,000
Committee of Adjustment Minor Variance (if required)Municipal Committee of Adjustment$1,000-$3,000
Electrical Safety Authority (ESA) PermitESA$150-$400
Plumbing PermitMunicipal or private inspector$100-$250
HVAC/Gas PermitTSSA$100-$200

infoBuilding permits for additions require full architectural/structural drawings — hand sketches are not sufficient. Expect to hire a designer ($3K-$8K) and structural engineer ($1.5K-$4K).

infoCommittee of Adjustment variances take 6-12 weeks and require neighbour notification. Objections can delay or kill the project — talk to neighbours early.

infoIf your addition creates a second dwelling unit (e.g., in-law suite with kitchen), additional requirements apply: fire separation, separate entrance, parking (unless exempt under Bill 23). See the Basement Second Unit service page.

infoEnergy code compliance (OBC 9.36) requires minimum R-values: walls R-20, ceilings R-50, basement walls R-12. Windows must meet energy rating (ER) minimums. Inspector may request insulation certificate or energy model.

infoIf building within 1.2m (4 feet) of a property line, OBC 9.10.15 requires fire-rated construction (1-hour rating, no openings). This affects window placement and wall assemblies.

infoTarion warranty does not apply to additions unless you hire a licensed builder enrolled in Tarion. Most homeowners hire contractors directly — no warranty. Protect yourself with detailed contracts and holdbacks (10% until deficiencies are corrected).

shield_lockPayment Protection

Milestone-Verified Payment Architecture

Every home additions project on RenoNext uses milestone-based escrow. Your funds are held securely and only released when work is verified at each stage.

  • lock

    Escrow-Held Funds

    Your money sits in a regulated escrow account, not the contractor's pocket.

  • verified

    Photo-Verified Milestones

    Each phase is documented and verified before payment is released.

  • account_balance

    10% Holdback Compliance

    Automatic CPA-compliant holdback ensures warranty protection.

See How Payments Workarrow_forward

Project Center

Home Additions

In Progress
check
Deposit15%
check
2. Design and Structural Engineering25%
3. Committee of Adjustment Variance (if needed)30%
Final + Holdback30%

Escrow Balance

$60,000-$120,000

lockSecured
warning

Addition Failures: The Junction is Where It Breaks

  • error**Differential settlement:** New foundations settle as soil compacts under load. Old foundations (50-100 years old) have already settled. If the new addition is tied rigidly to the old house, differential settlement causes cracks at the junction — vertical cracks in drywall, separated brick courses, stuck doors. The fix: independent foundations with a slip joint (expansion joint) at the interface, sealed with flexible flashing and caulk. Cost to repair after failure: $8K-$20K (underpin settling foundation, re-point brick, patch finishes).
  • error**Roof valley leaks:** Valleys are the #1 failure point in roof tie-ins. Water from both roof planes converges and flows fast down the valley. If valley flashing is undersized, improperly lapped, or missing ice/water shield underlayment, water backs up under shingles and leaks into the house. Symptoms: water stains on ceiling near the valley, mold in attic. The fix: strip shingles, install ice/water shield (36" wide minimum, extending 18" up each plane), install 24-gauge metal valley flashing (open valley, not closed), re-shingle with proper overlap. Cost: $1,500-$4,000 depending on valley length.
  • error**Kick-out flashing failure:** Where a roof meets a vertical wall (common in L-shaped additions), water running down the roof hits the wall and must be diverted away. Kick-out flashing is a bent metal piece at the bottom of the step flashing that directs water into the gutter. Without it, water runs behind the siding and into the wall cavity — causing rot, mold, and structural damage over 2-5 years. Repair cost: $5K-$15K (strip siding, replace rotted sheathing and framing, re-side). Kick-out flashing costs $50 and takes 15 minutes to install. No excuse for skipping it.
  • error**Thermal bridging and air leakage at the junction:** The seam between old and new construction is often poorly insulated and unsealed. Batt insulation doesn't seal air gaps — air leaks through the junction, carrying moisture into wall cavities (condensation, mold) and wasting energy (cold drafts, high heating bills). The solution: spray foam (closed-cell, 2" minimum) at the junction, taped air barrier (Tyvek, Blueskin) over sheathing seams, and continuous insulation (rigid foam or spray foam) across the transition. Cost to fix after construction: impossible without removing finishes. Do it right during framing.
  • error**Undersized footings for new loads:** If adding a second storey, the existing foundation must carry the added load. Foundations built before 1970 are often 8" thick with shallow footings (12" wide, 6" deep) — inadequate for two-storey loads. Adding weight without upgrading the foundation causes settling, cracking, and structural failure. A structural engineer calculates existing capacity and designs upgrades: underpinning (new footings below existing), thickening walls (shotcrete or poured concrete), or adding grade beams. Cost: $15K-$50K depending on scope. Skipping this step and hoping for the best is gambling with your house.
  • error**Zoning violations and unapproved variances:** Building an addition that violates setbacks without a Committee of Adjustment variance is illegal. The municipality can issue a stop-work order, force you to tear down the addition, or refuse occupancy. Even if you finish construction, you can't sell the house without resolving the violation — title insurance won't cover it, and buyers will walk away. Apply for the variance before you start. If denied, redesign or appeal. Don't build first and hope no one notices — neighbours report violations, and municipalities enforce them.

Trusted by Ontario Homeowners

RenoNext infrastructure protecting every home additions project

account_balance

$25M+

Escrow Protected

gpp_good

0.02%

Dispute Rate

verified

12k+

Milestones Verified

helpFAQ

Common Questions

How much does a home addition cost per square foot?expand_more
$200-$400 per square foot is typical for quality construction in Ontario. Simple one-storey additions on slab foundations are at the low end ($200-$250/sq ft). Second-storey additions or complex designs with multiple roof planes, custom finishes, or foundation upgrades are at the high end ($300-$400/sq ft). Budget 15-25% extra for design, permits, and contingencies. A 300 sq ft addition costs $60K-$120K all-in.
Do I need a Committee of Adjustment variance for my addition?expand_more
Only if your addition violates zoning bylaws — setbacks, lot coverage, or height. Check your municipality's zoning map and bylaws (available online or at city hall). Measure your lot and proposed addition. If it fits within zoning rules, no variance needed. If it encroaches on setbacks (e.g., less than 7.5m rear yard, or exceeds 35% lot coverage), apply for a minor variance. Process takes 6-12 weeks, costs $1,000-$3,000, and requires neighbour notification. Approval is common for reasonable requests, but neighbour opposition can delay or sink the project. Hire a land-use planner ($1,500-$3,000) if contentious.
Can I build an addition on my existing foundation, or do I need a new one?expand_more
Ground-floor additions always need new foundations — either independent (not connected to existing) or tied (connected with rebar). Independent foundations prevent differential settlement (new settles differently from old). Tied foundations create a monolithic structure but risk cracking if soils differ. Most engineers prefer independent with proper flashing at the joint. Second-storey additions build on the existing footprint — but the existing foundation must be strong enough to carry the added load. Foundations built before 1970 often need upgrades: underpinning, thickening walls, or adding grade beams. A structural engineer assesses capacity and designs upgrades ($1,500-$4,000).
How long does it take to build a home addition?expand_more
4-8 months from design to occupancy. Breakdown: design and engineering (3-6 weeks), permit approval (4-8 weeks, or 10-20 weeks if Committee of Adjustment variance needed), construction (12-20 weeks depending on size and complexity), final inspections (1-2 weeks). Weather delays, permit revisions, and material delivery issues add time. Second-storey additions take longer (16-24 weeks construction) due to foundation upgrades and roof complexity.
Do I need to upgrade my electrical panel or HVAC system for an addition?expand_more
Probably. Electrical: calculate the load of the addition (outlets, lights, appliances, heating). If your existing panel is 100A and heavily loaded, adding 30-40A of new circuits requires a service upgrade to 200A ($3K-$5K). If your panel is 200A with spare slots, a sub-panel may suffice ($1,500-$2,500). HVAC: calculate added square footage. If your furnace is undersized (most are sized 10-20% over original floor area, no more), extending ductwork overloads the system and creates comfort issues. Options: add a second furnace/AC ($6K-$12K), install a mini-split heat pump ($4K-$8K), or upgrade the main system ($8K-$15K). Your HVAC contractor will do a Manual J load calculation to determine needs.
What happens if the new addition settles differently from the old house?expand_more
Differential settlement causes cracks at the junction — vertical cracks in drywall, separated brick courses, doors that stick or won't close. It happens because new soil compacts under load over 1-5 years, while old foundations settled decades ago. Prevention: build independent foundations (not tied to existing) with an expansion joint at the interface, sealed with flexible flashing and polyurethane caulk. If you tie the foundations and differential settlement occurs, repair requires underpinning the settling foundation ($15K-$40K), re-pointing brick, and patching finishes. The crack will reopen unless you fix the settlement.
Can I DIY parts of the addition to save money?expand_more
Yes, but not structural, electrical, plumbing, or HVAC — those require licensed contractors and inspections. You can do: demolition (removing old siding, trim), painting, finish carpentry (baseboards, trim), flooring installation (laminate, LVP), and landscaping after construction. Savings: 10-20% of total cost if you do substantial finish work yourself. Do NOT attempt foundation work, framing, roofing, rough electrical, or rough plumbing — mistakes are expensive to fix and dangerous. ESA and building inspectors will not pass DIY structural or rough-in work unless you're a licensed tradesperson.
How do I match the existing siding and roofing on my addition?expand_more
Vinyl siding: easy — identify the profile and color, order matching material. Most profiles are still manufactured. Brick: difficult — matching coursing height, mortar color, and brick color is tricky. Old brick fades over decades; new brick looks different. Blend the transition with a feature strip (rowlock course, soldier course) or different material (stone accent). Roofing: if the existing roof is less than 10 years old, match the shingle brand and color. If older, re-roof the entire house during the addition for consistent appearance and warranty (shingle warranties don't cover patchwork roofing). Cost to re-roof whole house: $8K-$18K depending on size and pitch.
rocket_launch

Ready to start your home additions project?

Get matched with verified home additions pros in Ontario. Escrow-protected payments, GPS-verified work, and a permanent record of everything.

verified_userEscrow Protected
gpp_goodVetted Pros
shield_with_heart10% Holdback